2025 Construction to Begin
- lwittler
- Mar 10
- 2 min read
Hi everyone,
Construction for 2025 will resume on March 31st. Below is a summary of the upcoming work as well as an image of the updated phasing plan. A public meeting is being scheduled for the week of March 24th to review the project with property owners. The date and time will be provided in a separate update.
Phase 4 (Walnut Street and Grand Avenue):
Upcoming weeks: Crews will be on site in the upcoming days to start locating Sanitary Sewer and Water Services throughout the jobsite prior to removals.
3/31: Streets within Phase 4 will be closed to begin removals along Walnut Street and Grand Avenue. The contractor is estimating Phase 4 to be complete by the end of June.
Phase 5 (Ivy Lane)
Streets are scheduled to be closed for construction starting in June.
Phase 6 (Elm Street, Milwaukee Avenue, and Grand Avenue)
Upcoming weeks: Private Utilities Companies such as MidAmerican and Xcel will be on site relocating their facilities. Streets will be open to traffic while they perform their work.
Streets are scheduled to be closed for construction starting in May.
Phase 7 (Anna Way)
Streets are scheduled to be closed for construction starting in July.
Phase 1-3 (Perry Lane and Maple Street)
Reminder: Seeding window opens April 15th and closes May 15th. The Contractor will resume seeding and restoration throughout Phase 1-3. If your yard has irrigation, it can now be repaired. If you have not yet hired a landscaper to repair your irrigation, you can contact Darrel Miles, with Groundwater Landscape and Irrigation, at (605) 370-3772.
If there are any questions, please contact the project team. Thank you!