top of page
PROJECT UPDATES
Stay informed on how the Harrisburg SE Infrastructure project is progressing!
Subscribe to get email notifications letting you know that a new update has been posted.
Phase 1-3 Seeding
Hello Everyone, The contractor has finished seeding throughout last year's project. As a reminder, the City of Harrisburg will be...
jthier9
19 hours ago1 min read
91 views
0 comments


Project Information
Hi Everyone, On Monday, the 24th, the City of Harrisburg hosted an open house. Included with this post is a handout containing project...
jthier9
2 days ago1 min read
103 views
0 comments
Phase 4-7 Open House Reminder
Hey Everyone, The City of Harrisburg will be hosting an open house for the SE Infrastructure Project. What: Harrisburg SE...
jthier9
6 days ago1 min read
107 views
0 comments


Phase 1-3 Seeding
Hello Everyone, Crews will be onsite today performing finish grading work and seeding operations along last year's project. Attached to...
stockwellengineers
Mar 201 min read
280 views
0 comments
Phase 4-7 Removal Markings
Hi everyone, Trees, driveways, and other pavements will be marked for removal tomorrow and Friday, in anticipation of saw cutting...
jthier9
Mar 191 min read
139 views
0 comments
Phase 4-7 Open House Announcement
Hi everyone, The City of Harrisburg will be hosting an open house for the SE Infrastructure Project. Letters regarding the open house...
jthier9
Mar 171 min read
156 views
0 comments


2025 Construction to Begin
Hi everyone, Construction for 2025 will resume on March 31st. Below is a summary of the upcoming work as well as an image of the updated...
lwittler
Mar 102 min read
258 views
0 comments
Contact Information for Irrigation and Landscaping
Hi everyone, The previous update included an incorrect phone number for the landscaping and irrigation contractor. The correct number for...
ahutchings0
Oct 31, 20241 min read
96 views
0 comments


Project Status
Hi everyone, Construction for 2024 will be wrapping up within the next few weeks. Here is a summary of the remaining work. Phase 1-3...
ahutchings0
Oct 30, 20241 min read
201 views
0 comments


Schedule Update and Project Status
Hi everyone, Here is an updated project schedule, and since our last update, the Contractor has completed paving within Phase 3. Below is...
ahutchings0
Oct 24, 20241 min read
194 views
1 comment


Maple Street Paving Completed
Hi everyone, The concrete crews have completed paving along Maple Street. The road will remain closed to traffic through next week. If...
ahutchings0
Oct 18, 20241 min read
156 views
0 comments


Project Status
Hi everyone, Since our last update, the Contractor has installed most traffic signs, the majority of landscaping, and finished curb and...
ahutchings0
Oct 11, 20241 min read
232 views
0 comments


Project Status
Hi everyone, Since our last update, the Contractor has completed most of the grading and topsoil installation along Perry Lane, and the...
ahutchings0
Oct 2, 20241 min read
210 views
0 comments


Yard Restoration - Phase 1 and 2
Hi everyone, Construction crews have begun topsoil work south of Tiger Street, and will continue working north through Phase 1 and Phase...
ahutchings0
Sep 26, 20241 min read
173 views
0 comments


Project Status
Hi everyone, Since our last update, the Contractor finished the underground installation along Maple Street and has begun installing...
ahutchings0
Sep 19, 20241 min read
248 views
0 comments


Water Shutdown
Hi everyone, The Contractor will perform a water main connection near the intersection of Milwaukee and Maple on Monday (9/9). Water...
ahutchings0
Sep 6, 20241 min read
122 views
0 comments
Perry Lane Update
Hi everyone, Perry Lane is now open to traffic and street parking. Please be aware of the temporary traffic signs at the intersections....
ahutchings0
Sep 4, 20241 min read
256 views
0 comments


Project Status
Hello all, Since our last update, the Contractor finished concrete sidewalk and driveway work along Perry Avenue as well as installed...
stockwellengineers
Sep 3, 20241 min read
260 views
0 comments


Schedule Update
Hi everyone! Here is the updated project schedule. Construction will stop for 2024 once Phase 3 has been completed, and the remaining...
ahutchings0
Aug 28, 20241 min read
250 views
0 comments

Grand Ave & Maple St Intersection Closure
Greetings: Starting on Monday, 8/19 the intersection of Grand Ave and Maple Street will be closed to vehicular traffic for the duration...
stockwellengineers
Aug 16, 20241 min read
207 views
0 comments
bottom of page