Since our last update, the contractor has placed concrete driveways along Grand Avenue, Milwaukee Avenue, and Elm Street. Below is a summary of the work over the next week.
Elm Street, Milwaukee Avenue, and Grand Avenue (Phase 6B):
Next week: The contractor will be on site to place topsoil throughout disturbed areas of the project. When topsoil is in place, this phase will be substantially complete and open to traffic.
Anna Way (Phase 7B)
Next week: The contractor will continue constructing concrete driveways. Once all concrete driveways have been constructed, the contractor will be on site to place topsoil throughout disturbed areas of the project. When topsoil is in place, this phase will be substantially complete and open to traffic.
If you have any questions, please contact the project team. Thank you!


Who is the contractor doing the lawns?