Construction Update
- jthier9
- Jul 3
- 2 min read
Since our last update, the contractor has started underground utilities on Anna Way and Phase 4 has been opened to traffic. Please note that the contractor plans to begin removals in Phase 6B on the 21st of July.
Phase 4 (Walnut Street):
Next week: Walnut Street and Grand Avenue is now open to traffic. Mailboxes and Traffic Signs will be reset throughout Phase 4 early next week. Please note that seeding operations will begin in the fall due to the hot temperatures. If you are in need of a contractor for irrigation repair, you can contact Darrel Miles, with Groundwater Landscape and Irrigation, at 605-370-3722.
Phase 5 (Ivy Lane):
Next week: Grading crews will be on site placing topsoil along disturbed areas of the project. Ivy Lane will remain closed until the topsoil is in place along Ivy Lane.
Phase 6A (Elm Street):
Next week: Storm sewer boxes throughout Phase 6A will be constructed in preparation for curb and gutter.
Week of 7/14: Concrete crews will be on site to prepare to place curb and gutter along Elm Street. Once the curb and gutter is in place the concrete crew will begin constructing concrete driveways.
Phase 7A (Anna Way):
Next Week: The underground utility crew will install sanitary sewer, watermain, and storm sewer throughout the week.
Week of 7/14: Utilities will continue to be installed throughout Phase 7A including sanitary sewer, watermain, and storm sewer.
Phase 6B (Milwaukee and Grand Avenue):
Next week: The contractor plans to begin removals on Monday, the 21st of July. Once work begins, residents will not have access to their driveways and will need to park outside of the construction limits or make other arrangements.
If you have any questions, please contact the project team. Thank you!