Since our last update, the contractor has placed curb and gutter and began constructing driveway approaches along Elm Street, Milwaukee Avenue, and Grand Avenue. Below is a summary of the work over the next couple of weeks.
Elm Street, Milwaukee Avenue, and Grand Avenue (Phase 6B):
Next week: The contractor plans to prepare the road for Asphalt surfacing on Monday and Tuesday. The contractor is estimating that asphalt pavement will be placed on Wednesday and Thursday. Once the asphalt is in place, the contractor will construct concrete driveways.
Week of 9/29: When all concrete and asphalt surfacing is in place, the contractor will be on site to place topsoil throughout disturbed areas of the project. When topsoil is in place, this phase will be substantially complete and open to traffic.
Anna Way (Phase 7B)
Next week: The contractor will now prepare the road for concrete curb and gutter. Once curb and gutter is in place, the contractor will place concrete approaches.
Week of 9/29: Concrete crews will be on site placing concrete approaches. When approaches are constructed, asphalt surfacing will be placed.