top of page
Search

Construction Update

  • jthier9
  • Aug 15
  • 1 min read

Since our last update, the contractor has placed curb and gutter along Phase 7A and installed underground utilities along Phase 6B. Below is a summary of the work over the next couple of weeks.


Phase 6A (Elm Street):

  • On Wednesday, August 13th, the contractor began seeding operations throughout Phase 6A. If you have any questions regarding lawn maintenance, please find the lawn maintenance guide below.


Phase 6B (Milwaukee and Grand Avenue):

  • Next week: The contractor will continue to install underground utilities throughout Phase 6B. Once the Sanitary Sewer is installed, the contractor will begin installing watermain.

  • Week of 8/25: Storm sewer facilities will be installed throughout Phase 6B during the week of the 25th.


Phase 7A (Anna Way):

  • Next week: Early next week, the contractor plans to prepare the street for asphalt surfacing. Currently, asphalt surfacing is tentatively planned to start on Wednesday.

  • Week of 8/25: Once asphalt surfacing is in place, the contractor will place concrete driveways throughout the week.


Phase 7B (Anna Way)

  • Week of 8/25: The contractor is planning to begin removals throughout Phase 7B on August 25th. Once work begins, residents will not have access to their driveways and will need to park outside of the construction limits or make other arrangements.


If you have any questions, please contact the project team. Thank you!



 
 
 

Recent Posts

See All
Surfacing Warranty

Hello everyone, Tomorrow, the contractor will begin surfacing warranty repairs for work completed throughout the first year of construction. Please note that some sidewalk sections may be closed for s

 
 
 

1 Comment


JSTAPLETON86
Aug 16

When are they going to come and seed walnut Street? also I think some spots need to be regraded due to all the rain we've had with no seed or grass its washed away spots now exposing alot of roots and not as filled as it should be.

Edited
Like

Subscribe here to receive project updates to your inbox.

Thanks for subscribing!

City of Harrisburg Seal (Color).png

City of Harrisburg

 

(605) 743-5872

301 E Willow St.

Harrisburg, SD 57032

harrisburgsd.gov

Stockwell Engineers

(605) 338-6668

801 N Phillips Ave

Ste. 100

Sioux Falls, SD 57104

stockwellengineers.com

HARRISBURG SE INFRASTRUCTURE IMPROVEMENTS
PROJECT INFORMATION SITE

bottom of page