Hi everyone! Here is a quick update regarding the project schedule and what has been completed to date.

 

Underground utilities are nearly complete for both Phase 1 and 2. We are waiting for the water quality tests results before connecting the last remaining houses onto the new water main. Crews will continue installing storm sewer north of Walnut Street and the storm structures. During the next few weeks, crews will be onsite to complete removals (including the sidewalk) and grading the surface for the new road.


Phase 3 is anticipated to start at the end of July or early August, starting with road closures and demolition. Please note that the schedule presented at this time is an estimate.


If you anyone has questions regarding the project, please feel free to reach out to Mitch Mergen at (605) 338-6668 for more information. Thank you for your patience and accommodation during this project!


ree

 
 
 

Recent Posts

See All
Surfacing Warranty

Hello everyone, Tomorrow, the contractor will begin surfacing warranty repairs for work completed throughout the first year of construction. Please note that some sidewalk sections may be closed for s

 
 
 

Comments


Subscribe here to receive project updates to your inbox.

Thanks for subscribing!

City of Harrisburg Seal (Color).png

City of Harrisburg

 

(605) 743-5872

301 E Willow St.

Harrisburg, SD 57032

harrisburgsd.gov

Stockwell Engineers

(605) 338-6668

801 N Phillips Ave

Ste. 100

Sioux Falls, SD 57104

stockwellengineers.com

HARRISBURG SE INFRASTRUCTURE IMPROVEMENTS
PROJECT INFORMATION SITE

bottom of page