top of page
Search

Project Status

  • jthier9
  • May 2
  • 1 min read

Hello everyone,


Since our last update, the Contractor has installed utilities in Phase 4 and completed removals in Phase 5. Below is a summary of work scheduled to occur over the next two weeks.


Phase 4: (Walnut Street and Grand Avenue)

  • Week of 5/5: Utility crews will complete the installation of the remaining storm sewer along Walnut Street and connect the remaining water services. Early in the week, concrete crews will pour the storm sewer boxes. After all the storm sewer boxes are in place, the grading crew will arrive to shape the road and place the aggregate base course.

    *Please note that Walnut Circle will be closed to traffic while the grading crew is on site. The road closure is tentatively setup for Thursday-Friday. We will provide another update once there is a set road closure date.

  • Week of 5/12: Grading crew will be on site early in the week installing base course. Once base course is in place, the concrete crew will begin pouring the curb and gutter along Walnut and Grand Ave.


Phase 5: (Ivy Lane)

  • Week of 5/5: At the start of the week, utility crews will be on-site to connect temporary water services. For the rest of the week, the installation of the sanitary sewer will take place.

  • Week of 5/12: Utility crew will be on-site installing watermain and storm sewer throughout Ivy Lane.


If you have any questions, please contact the project team. Thank you!



 
 
 

Opmerkingen


Subscribe here to receive project updates to your inbox.

Thanks for subscribing!

City of Harrisburg Seal (Color).png

City of Harrisburg

 

(605) 743-5872

301 E Willow St.

Harrisburg, SD 57032

harrisburgsd.gov

Stockwell Engineers

(605) 338-6668

801 N Phillips Ave

Ste. 100

Sioux Falls, SD 57104

stockwellengineers.com

HARRISBURG SE INFRASTRUCTURE IMPROVEMENTS
PROJECT INFORMATION SITE

bottom of page