Hello all,

The Contractor has returned to the site after the long Holiday weekend to continue their work. Below is a summary of work planned to occur over the next two weeks assuming cooperative weather. If anyone has questions, please reach out to the project team. Thank you!


Phase 1

  • This week: Private utility companies will relocate various facilities so they are out of the Contractor's way

  • This week: Sidewalks and the remaining driveway pavements will be removed in advance of earthwork crews (tentatively planned for Wednesday).

  • This week: Earthwork crews will begin preparing the roadbed for gravel

  • Next week: Gravel base will be installed

  • Next week: Contractor will prepare site for concrete curb and gutter.


Phase 2

  • This week: Underground crews plan to finish the remaining utility work

  • Next week: Private utility companies will relocate various facilities

  • Next week: Earthwork crews will begin preparing the roadbed for gravel.


ree
Underground Crews Proceeding with Work

 
 
 

Recent Posts

See All
Surfacing Warranty

Hello everyone, Tomorrow, the contractor will begin surfacing warranty repairs for work completed throughout the first year of construction. Please note that some sidewalk sections may be closed for s

 
 
 

Comments


Subscribe here to receive project updates to your inbox.

Thanks for subscribing!

City of Harrisburg Seal (Color).png

City of Harrisburg

 

(605) 743-5872

301 E Willow St.

Harrisburg, SD 57032

harrisburgsd.gov

Stockwell Engineers

(605) 338-6668

801 N Phillips Ave

Ste. 100

Sioux Falls, SD 57104

stockwellengineers.com

HARRISBURG SE INFRASTRUCTURE IMPROVEMENTS
PROJECT INFORMATION SITE

bottom of page