Project Status
- stockwellengineers

- Jul 8, 2024
- 1 min read
Hello all,
The Contractor has returned to the site after the long Holiday weekend to continue their work. Below is a summary of work planned to occur over the next two weeks assuming cooperative weather. If anyone has questions, please reach out to the project team. Thank you!
Phase 1
This week: Private utility companies will relocate various facilities so they are out of the Contractor's way
This week: Sidewalks and the remaining driveway pavements will be removed in advance of earthwork crews (tentatively planned for Wednesday).
This week: Earthwork crews will begin preparing the roadbed for gravel
Next week: Gravel base will be installed
Next week: Contractor will prepare site for concrete curb and gutter.
Phase 2
This week: Underground crews plan to finish the remaining utility work
Next week: Private utility companies will relocate various facilities
Next week: Earthwork crews will begin preparing the roadbed for gravel.



Comments