Hello all,

Over the last couple weeks the Contractor finished street paving and started sidewalk and approach work along Perry Avenue. Work also started on Phase 3, Maple Street, where removals are now complete and prep work for utilities occurred this week. Crews will continue to progress along all phases of the project. Below is a summary of work planned to occur over the next two weeks.


Phase 1 & 2 (Perry Ave)

  • Next week: Crews will start rebuilding concrete driveways

  • Week of 8/26: Crews will continue the remaining concrete work along Perry

  • Week of 9/2: Crews plan to place topsoil and restore yards

    Note: Residents who have irrigation or underground fence that was damaged due to the project, please notify your contractor's and tentatively schedule your repairs for the week of 9/2.


Phase 3 (Maple Street)

  • Next week: Underground crews will start sanitary sewer construction

  • Week of 8/26: Crews will continue underground work


ree
View of Perry Lane looking north


 
 
 

Recent Posts

See All
Surfacing Warranty

Hello everyone, Tomorrow, the contractor will begin surfacing warranty repairs for work completed throughout the first year of construction. Please note that some sidewalk sections may be closed for s

 
 
 

Comments


Subscribe here to receive project updates to your inbox.

Thanks for subscribing!

City of Harrisburg Seal (Color).png

City of Harrisburg

 

(605) 743-5872

301 E Willow St.

Harrisburg, SD 57032

harrisburgsd.gov

Stockwell Engineers

(605) 338-6668

801 N Phillips Ave

Ste. 100

Sioux Falls, SD 57104

stockwellengineers.com

HARRISBURG SE INFRASTRUCTURE IMPROVEMENTS
PROJECT INFORMATION SITE

bottom of page