top of page
Search

Project Status

  • ahutchings0
  • Oct 2, 2024
  • 1 min read

Hi everyone,


Since our last update, the Contractor has completed most of the grading and topsoil installation along Perry Lane, and the sanitary sewer improvements have been completed on 274th Street. Concrete crews have begun curb and gutter installation along Maple Street. Below is a summary of work planned to occur throughout the next few weeks.


Phase 1 & 2 (Perry Ave):

  • This week: Concrete crews will install sidewalks and ADA ramps at the Walnut and Maple intersections. Landscaping crews will continue to work on retaining walls and landscaping where necessary.

  • Next week: Crews are scheduled to reinstall mailboxes and traffic signs. Please ensure that your mailbox can easily be accessed by the contractor.

  • Note: Seeding has been postponed until Spring. The contractor will place mulch over the dirt and apply weed control before placing the seed in Spring. If your yard has irrigation, they can now be repaired.

    • If you have not yet acquired a landscaper to repair your irrigation, you can contact Darrel Miles, with Groundwater Landscape and Irrigation, at 605-370-3772.


Phase 3 (Maple St):

  • This week and next week: Earthwork crews will finish grading the roadway, installing gravel base course and preparing for concrete work from the railroad tracks to Grand Ave. Concrete crews will work from Perry Ln to Grand Ave completing curb and gutter, ADA ramps and concrete street paving. Note: concrete sawing will occur during nighttime hours.


If you have any questions, please contact the project team. Thank you!


ree
Grading and topsoil along Perry Lane

ree
Curb and gutter along Maple Street

 
 
 

Recent Posts

See All
Surfacing Warranty

Hello everyone, Tomorrow, the contractor will begin surfacing warranty repairs for work completed throughout the first year of construction. Please note that some sidewalk sections may be closed for s

 
 
 

Comments


Subscribe here to receive project updates to your inbox.

Thanks for subscribing!

City of Harrisburg Seal (Color).png

City of Harrisburg

 

(605) 743-5872

301 E Willow St.

Harrisburg, SD 57032

harrisburgsd.gov

Stockwell Engineers

(605) 338-6668

801 N Phillips Ave

Ste. 100

Sioux Falls, SD 57104

stockwellengineers.com

HARRISBURG SE INFRASTRUCTURE IMPROVEMENTS
PROJECT INFORMATION SITE

bottom of page