Project Status
- ahutchings0
- Oct 11, 2024
- 1 min read
Hi everyone,
Since our last update, the Contractor has installed most traffic signs, the majority of landscaping, and finished curb and gutter installation along Maple Street. Below is a summary of work planned to occur throughout the upcoming weeks.
Phase 1 & 2 (Perry Lane):
Next week: Landscaping crews will continue work on retaining walls and landscaping where necessary. Crews that installed mailboxes will coordinate with the Post Office to ensure all mailboxes meet regulations.
Week of 10/21: Application of mulch on the black dirt is tentatively scheduled for this week. Representatives from the City will perform a walkthrough along Phase 1 & 2 and create a punch list of items for the contractor to address before closing out those phases for 2024.
Reminder: Seeding has been postponed until Spring. If your yard has irrigation, they can now be repaired. If you have not yet acquired a landscaper to repair your irrigation, you can contact Darrel Miles, with Groundwater Landscape and Irrigation, at 605-370-3772.
Phase 3 (Maple St):
Next week: Concrete crews will install the remaining concrete, ADA ramps and driveway approaches. Concrete street paving is scheduled for Wednesday, 10/16.
Note: concrete sawing will occur during nighttime hours.
Week of 10/21: Concrete crews will start rebuilding driveways. Asphalt crews will pave within the intersections of Grand Ave and Milwaukee Street.
If you have any questions, please contact the project team. Thank you!