Schedule Update

  • jthier9
  • Jun 4
  • 1 min read

Hello everyone,


Since our last update, the Contractor has installed utilities throughout Phase 5 and began concrete surfacing throughout Phase 4.

Below is a summary of work scheduled to occur over the next two weeks.


Phase 4:

  • Next week: Asphalt surfacing is tentatively planned to begin on Monday the 9th of June. The remainder of the week will consist of the concrete crews pouring concrete driveways.

  • Week of 6/16: Once all of the concrete is in place, the contractor will begin placing topsoil throughout areas that were disturbed during the construction process.


Phase 5:

  • Next week: Concrete crews will move into Phase 5 throughout next week beginning with curb and gutter followed by concrete approaches.

  • Week of 6/16: The contractor is estimating that asphalt surfacing will begin early during the week. Once the asphalt is in place the contractor will begin placing topsoil throughout the disturbed areas.


Phase 6A:

  • Next week: Utility crews will be on site installing sanitary sewer and watermain.

  • Week of 6/16: Once sanitary sewer and watermain are in place, the contractor will start installing storm sewer throughout Phase 6A.


Phase 7A:

  • Week of 6/16: The contractor plans to begin removals on the 16th of June. Once work begins, residents will not have access to their driveways and will need to park outside of the construction limits or make other arrangements.


If you have any questions, please contact the project team. Thank you!



 
 
 

Kommentare


Subscribe here to receive project updates to your inbox.

Thanks for subscribing!

City of Harrisburg Seal (Color).png

City of Harrisburg

 

(605) 743-5872

301 E Willow St.

Harrisburg, SD 57032

harrisburgsd.gov

Stockwell Engineers

(605) 338-6668

801 N Phillips Ave

Ste. 100

Sioux Falls, SD 57104

stockwellengineers.com

HARRISBURG SE INFRASTRUCTURE IMPROVEMENTS
PROJECT INFORMATION SITE

bottom of page