Schedule Update
- jthier9
- Jun 4
- 1 min read
Hello everyone,
Since our last update, the Contractor has installed utilities throughout Phase 5 and began concrete surfacing throughout Phase 4.
Below is a summary of work scheduled to occur over the next two weeks.
Phase 4:
Next week: Asphalt surfacing is tentatively planned to begin on Monday the 9th of June. The remainder of the week will consist of the concrete crews pouring concrete driveways.
Week of 6/16: Once all of the concrete is in place, the contractor will begin placing topsoil throughout areas that were disturbed during the construction process.
Phase 5:
Next week: Concrete crews will move into Phase 5 throughout next week beginning with curb and gutter followed by concrete approaches.
Week of 6/16: The contractor is estimating that asphalt surfacing will begin early during the week. Once the asphalt is in place the contractor will begin placing topsoil throughout the disturbed areas.
Phase 6A:
Next week: Utility crews will be on site installing sanitary sewer and watermain.
Week of 6/16: Once sanitary sewer and watermain are in place, the contractor will start installing storm sewer throughout Phase 6A.
Phase 7A:
Week of 6/16: The contractor plans to begin removals on the 16th of June. Once work begins, residents will not have access to their driveways and will need to park outside of the construction limits or make other arrangements.
If you have any questions, please contact the project team. Thank you!
Kommentare