Schedule Update
- jthier9
- Jun 13
- 1 min read
Since our last update, the contractor constructed concrete driveways along Walnut Street and installed underground utilities along Elm Street. Please note that the contractor plans to begin removals in Phase 7A on the 23rd of June. Below is a summary of work scheduled to occur over the next two weeks.
Phase 4 (Walnut Street):
Next week: Concrete surfacing along Phase 4 will continue throughout next week. Once all the driveways have been constructed, the contractor will begin placing topsoil throughout areas that were disturbed during construction.
Week of 6/23: Once all topsoil is in place, the contractor plans to open Phase 4 to traffic.
Phase 5 (Ivy Lane):
Next week: The contractor plans to install asphalt throughout Ivy Lane on Tuesday and Wednesday. Once the asphalt is in place, the contractor will continue to construct driveways throughout Phase 5.
Week of 6/23: Once all the concrete driveways are in place, the contractor will begin placing topsoil throughout areas that were disturbed during construction.
Phase 6A (Elm Street):
Next week: Utility crews will connect water services and install Storm Sewer facilities along Elm Street.
Week of 6/23: Once all underground utilities are complete, the contractor will begin placing gravel and concrete curb and gutter throughout Elm Street.
Phase 7A (Elm Street):
Week of 6/23: The contractor plans to begin removals on the 23rd of June. Once work begins, residents will not have access to their driveways and will need to park outside of the construction limits or make other arrangements.
If you have any questions, please contact the project team. Thank you!