Schedule Update
- jthier9
- Jun 19
- 2 min read
Since our last update, the contractor has constructed concrete driveways along Walnut Street and installed underground utilities along Elm Street. Please note that the contractor plans to begin removals in Phase 7A on the 23rd of June and Phase 6B on the 25th of June. Below is a summary of work scheduled to occur over the next two weeks.
Phase 4 (Walnut Street):
Next week: The contractor has constructed all the driveways along Walnut Street and Grand Avenue. The road will remain closed until the topsoil is in place. The grading crew will be on site throughout next week placing topsoil throughout areas that were disturbed during construction.
Phase 5 (Ivy Lane):
Next week: Throughout next week, the concrete crews will construct concrete driveways along Ivy Lane.
Week of 6/30: Grading crews will be on site placing topsoil along disturbed areas of the project. Ivy Lane will remain closed until the topsoil is in place along Ivy Lane.
Phase 6A (Elm Street):
Next week: Storm sewer boxes throughout Phase 6A will be constructed in preparation for curb and gutter.
Week of 6/30: Concrete crews will be on site to prepare to place curb and gutter along Elm Street. Once the curb and gutter is in place the concrete crew will begin constructing concrete driveways.
Phase 7A (Anna Way):
Next Week: The contractor plans to begin removals on Monday, the 23rd of June. Once work begins, residents will not have access to their driveways and will need to park outside of the construction limits or make other arrangements. Once removals are complete, the utility crew will begin installing Sanitary Sewer along Phase 7A.
Week of 6/30: Utilities will continue to be installed throughout Phase 7A including sanitary sewer, watermain, and storm sewer.
Please Note: In order to provide access for the ongoing construction, the East side of Anna Way (Phase 7B) will have no parking signs.
Phase 6B (Milwaukee and Grand Avenue):
Next week: The contractor plans to begin removals on Wednesday, the 25th of June. Once work begins, residents will not have access to their driveways and will need to park outside of the construction limits or make other arrangements.
Week of 6/30: Utility crews will move into Phase 6B once the utilities in Phase 7A are installed. Utility facilities to be installed throughout Phase 6B include sanitary sewer, watermain, and storm sewer.
If you have any questions, please contact the project team. Thank you!


Comments