Schedule Update
Since our last update, the contractor constructed concrete driveways along Walnut Street and installed underground utilities along Elm...
jthier9
Jun 131 min read


Schedule Update
Hello everyone, Since our last update, the Contractor has installed utilities throughout Phase 5 and began concrete surfacing throughout...
jthier9
Jun 41 min read


Schedule Update
Hello everyone, Due to the upcoming weather forecast, the contractor has decided to delay Phase 7A construction. The Contractor is...
jthier9
May 191 min read


Schedule Update
Hello everyone, To help accommodate access and parking throughout the job site, the Contractor will be adjusting their sequencing plan....
jthier9
May 81 min read


Walnut Circle Closure
Walnut Circle will be closed to traffic on Tuesday, May 13th. During this closure, residents will not have access to their driveways and...
jthier9
May 81 min read


Water Shutdown
Hello everyone, The Contractor will perform a water main connection on Ivy Lane. This water main connection will require a water shutdown...
jthier9
May 71 min read


Water Shutdown
Hello everyone, The Contractor will perform a water main connection on Ivy Lane. This water main connection will require a water shutdown...
jthier9
May 61 min read


Landscaping and Irrigation Repairs
Hello everyone, Groundwater Landscape and Irrigation will be on-site throughout the upcoming days. If you have any landscaping or...
jthier9
May 51 min read


Project Status
Hello everyone, Since our last update, the Contractor has installed utilities in Phase 4 and completed removals in Phase 5. Below is a...
jthier9
May 21 min read


Water Shutdown
Hello everyone, The Contractor will be connecting the new water main to the existing water main West of the Grand and Walnut intersection...
jthier9
May 21 min read


Phase 1-3 Seeding
Hello Everyone, The spring growing season is upon us and the seed installed by the Contractor a few weeks ago along Perry Street and...

stockwellengineers
Apr 251 min read


Phase 5 - Ivy Lane Closure and Temporary Mailboxes
Hi everyone! The contractor is planning to begin Phase 5 on Monday (4/28), weather pending. Ivy Lane will be closed Monday morning to...
ahutchings0
Apr 241 min read


Schedule Update
Hi everyone! Here is a quick update regarding the project schedule. The PDF attached shows the updated phasing sequence for the remainder...
jthier9
Apr 111 min read


Water Shutdown
Hello Everyone, The Contractor will perform a water main cut and cap near the intersection of Walnut and Grand on Tuesday(4/15). Water...
jthier9
Apr 111 min read
Phase 1-3 Seeding
Hello Everyone, The contractor has finished seeding throughout last year's project. As a reminder, the City of Harrisburg will be...
jthier9
Mar 271 min read


Project Information
Hi Everyone, On Monday, the 24th, the City of Harrisburg hosted an open house. Included with this post is a handout containing project...
jthier9
Mar 251 min read
Phase 4-7 Open House Reminder
Hey Everyone, The City of Harrisburg will be hosting an open house for the SE Infrastructure Project. What: Harrisburg SE...
jthier9
Mar 211 min read


Phase 1-3 Seeding
Hello Everyone, Crews will be onsite today performing finish grading work and seeding operations along last year's project. Attached to...

stockwellengineers
Mar 201 min read
Phase 4-7 Removal Markings
Hi everyone, Trees, driveways, and other pavements will be marked for removal tomorrow and Friday, in anticipation of saw cutting...
jthier9
Mar 191 min read
Phase 4-7 Open House Announcement
Hi everyone, The City of Harrisburg will be hosting an open house for the SE Infrastructure Project. Letters regarding the open house...